74 Rows |
Docket Number |
Description & Type |
Page Count |
On Behalf Of |
Filed By |
Date Filed |
1 |
1 |
Application for Certificate of Site Compatibility
Application
|
199 |
Basin Electric Power Cooperative |
Todd Telesz, CEO, GM |
2022.10.07 |
2 |
2 |
Receipt# 11,455 $100,000.00 Application Fee
Receipt
|
1 |
Basin Electric Power Cooperative |
|
2022.10.12 |
3 |
3 |
Receipt# 11,456 $25,000.00 Administrative Fee
Receipt
|
1 |
Basin Electric Power Cooperative |
|
2022.10.12 |
4 |
4 |
Siting Admin Fee
Other
|
2 |
Public Service Commission |
|
2022.10.12 |
5 |
5 |
Request for ALJ
Other
|
3 |
Public Service Commission |
John Schuh, General Counsel |
2022.11.07 |
6 |
6 |
Letter designating Administrative Law Judge - Timothy Dawson
Letter
|
1 |
Office of Administrative Hearings |
Timothy Dawson, Director |
2022.11.09 |
7 |
7 |
Supplemental Information to Application
Other
|
2 |
Basin Electric Power Cooperative |
Kevin Solie |
2022.11.18 |
8 |
8 |
Commission Motion to deem application complete and issue Notice
Motion
|
1 |
Public Service Commission |
|
2022.11.30 |
9 |
9 |
Notice of Filing and Notice of Public Hearing
Notice
|
2 |
Public Service Commission |
|
2022.11.30 |
10 |
10 |
Emails to-from NDNA re publication of Notice
Other
|
4 |
North Dakota Newspaper Association |
|
2022.12.01 |
11 |
11 |
Affidavit of Service Reg. and E-mail - Notice of Filing and Notice of Public Hearing
Affidavit
|
7 |
Public Service Commission |
|
2022.12.01 |
12 |
12 |
Affidavit of Service Cert. and Reg. - Notice of Filing and Notice of Public Hearing
Affidavit
|
4 |
Public Service Commission |
|
2022.12.01 |
13 |
13 |
Notice of Appearance - Anine A. Merkens
Letter
|
2 |
Basin Electric Power Cooperative |
Anine Merkens |
2022.12.05 |
14 |
14 |
Letter regarding court reporter retained for Jan. 5, 2023 formal hearing
Letter
|
1 |
Basin Electric Power Cooperative |
Anine Merkens |
2022.12.05 |
15 |
15 |
Return receipt
Other
|
2 |
United States Postal Service |
|
2022.12.07 |
16 |
16 |
Agency Correspondence
Letter
|
7 |
North Dakota Department of Environmental Quality (DEQ) |
L. David Glatt, P.E., Director |
2022.12.12 |
17 |
17 |
Letter enclosing prefiled Direct Testimony and Exhibits
Letter
|
1 |
Basin Electric Power Cooperative |
Anine Merkens |
2022.12.27 |
18 |
18 |
Prefiled Testimony of James Lund
Other
|
12 |
Basin Electric Power Cooperative |
Anine Merkens |
2022.12.27 |
19 |
19 |
Prefiled Testimony of Benjamin Hertz
Other
|
5 |
Basin Electric Power Cooperative |
Anine Merkens |
2022.12.27 |
20 |
20 |
Prefiled Testimony of Kevin Solie
Other
|
9 |
Basin Electric Power Cooperative |
Anine Merkens |
2022.12.27 |
21 |
21 |
Prefiled Exhibit 1 - Map View
Exhibit
|
1 |
Basin Electric Power Cooperative |
Anine Merkens |
2022.12.27 |
22 |
22 |
Prefiled Exhibit 2 - Figure1-2 Site Layout Aerial Map
Exhibit
|
1 |
Basin Electric Power Cooperative |
Anine Merkens |
2022.12.27 |
23 |
23 |
Prefiled Exhibit 3 - Figure1-3 Site Layout Topo Map
Exhibit
|
1 |
Basin Electric Power Cooperative |
Anine Merkens |
2022.12.27 |
24 |
24 |
Prefiled Exhibit 4 - Figure 4-4 Water Features Map
Exhibit
|
1 |
Basin Electric Power Cooperative |
Anine Merkens |
2022.12.27 |
25 |
25 |
Prefiled Exhibit 5 - Interconnection Requests and Acceptance to SPP Impact Study
Exhibit
|
15 |
Basin Electric Power Cooperative |
Anine Merkens |
2022.12.27 |
26 |
26 |
Prefiled Exhibit 6 - USACE Jurisdictional Determination - No Permit Required
Exhibit
|
5 |
Basin Electric Power Cooperative |
Anine Merkens |
2022.12.27 |
27 |
27 |
Revised Prefiled Exhibit 2 - Figure1-2 Site Layout Aerial Map
Exhibit
|
1 |
Basin Electric Power Cooperative |
Kevin Solie |
2023.01.03 |
28 |
28 |
Invoice, $482.32
Invoice
|
1 |
North Dakota Newspaper Association |
|
2023.01.09 |
29 |
29 |
Affidavit of Publication with tear sheets
Other
|
5 |
North Dakota Newspaper Association |
|
2023.01.09 |
30 |
30 |
Letter enclosing sign-in sheet, audio, witness and exhibit lists, and Exhibits
Letter
|
1 |
Timothy Dawson, ALJ - Office of Administrative Hearings |
|
2023.01.11 |
31 |
31 |
Hearing sign-in sheet
Other
|
1 |
Timothy Dawson, ALJ - Office of Administrative Hearings |
|
2023.01.11 |
32 |
32 |
Electronic recording of 5 Jan. 2023 formal hearing
Audio
|
1 |
Public Service Commission |
|
2023.01.05 |
33 |
33 |
Witness List
Other
|
1 |
Timothy Dawson, ALJ - Office of Administrative Hearings |
|
2023.01.11 |
34 |
34 |
Exhibit List
Other
|
1 |
Timothy Dawson, ALJ - Office of Administrative Hearings |
|
2023.01.11 |
35 |
35 |
Exhibit 1 - Map View
Exhibit
|
1 |
Basin Electric Power Cooperative |
|
2023.01.05 |
36 |
36 |
Exhibit 2 - Site Layout Aerial Map
Exhibit
|
1 |
Basin Electric Power Cooperative |
|
2023.01.05 |
37 |
37 |
Exhibit 3 - Site Layout Topo Map
Exhibit
|
1 |
Basin Electric Power Cooperative |
|
2023.01.05 |
38 |
38 |
Exhibit 4 - Water Features Map
Exhibit
|
1 |
Basin Electric Power Cooperative |
|
2023.01.05 |
39 |
39 |
Exhibit 5 - Interconnection Requests and Acceptance to SPP Impact Study
Exhibit
|
15 |
Basin Electric Power Cooperative |
|
2023.01.05 |
40 |
40 |
Exhibit 6 - USACE Jurisdictional Determination - No Permit Required
Exhibit
|
5 |
Basin Electric Power Cooperative |
|
2023.01.05 |
41 |
41 |
Exhibit 7 - Supplemental Information to Application
Exhibit
|
2 |
Basin Electric Power Cooperative |
|
2023.01.05 |
42 |
42 |
January 5, 2023 Hearing Transcript (Full and Condensed)
Other
|
178 |
Emineth & Associates Court Reporters |
Stephanie Smith |
2023.01.18 |
43 |
43 |
Certification Relating to Order Provisions
Other
|
6 |
Basin Electric Power Cooperative |
Anine Merkens |
2023.01.19 |
44 |
44 |
Proposed Findings of Fact, Conclusions of Law and Order
Other
|
7 |
Basin Electric Power Cooperative |
Anine Merkens |
2023.01.19 |
45 |
45 |
Commission motion to adopt the Findings of Fact, Conclusions of Law and Order
Motion
|
1 |
Public Service Commission |
|
2023.02.08 |
46 |
46 |
Findings of Fact, Conclusions of Law and Order
Order
|
14 |
Public Service Commission |
|
2023.02.08 |
47 |
47 |
Letter closing OAH file
Letter
|
1 |
Timothy Dawson, ALJ - Office of Administrative Hearings |
|
2023.02.10 |
48 |
48 |
Affidavit of Service by Certified Mail - Findings of Fact, Conclusions of Law and Order
Affidavit
|
16 |
Public Service Commission |
|
2023.02.10 |
49 |
49 |
Executed Contract
Other
|
15 |
Public Service Commission |
|
2023.02.15 |
50 |
50 |
Letter enclosing executed contract
Letter
|
16 |
Public Service Commission |
|
2023.02.15 |
51 |
51 |
Return receipts (2)
Other
|
4 |
United States Postal Service |
|
2023.02.21 |
52 |
52 |
Request to begin construction and waiver request
Letter
|
34 |
Basin Electric Power Cooperative |
James Lund, Project Coordinator |
2023.02.24 |
53 |
53 |
Preconstruction Minutes and Notice of Intent to Start Construction
Notice
|
2 |
Basin Electric Power Cooperative |
|
2023.02.24 |
54 |
54 |
Memorandum
Memo
|
1 |
Public Service Commission |
Adam Renfandt |
2023.02.27 |
55 |
55 |
Commission motion to approve the removal of frozen topsoil using the method in the filing on February 24, 2023
Motion
|
1 |
Public Service Commission |
|
2023.03.08 |
56 |
56 |
Letter enclosing Commission motion
Letter
|
2 |
Public Service Commission |
|
2023.03.09 |
57 |
57 |
Letter Notice that start date of construction delayed until March 20, 2023
Letter
|
1 |
Basin Electric Power Cooperative |
Erin Fox Dukart, Director |
2023.03.10 |
58 |
58 |
FAA Temporary Structure Letters regarding Project
Letter
|
42 |
Basin Electric Power Cooperative |
Erin Fox Dukart |
2023.03.13 |
59 |
59 |
Williams County Approach Permits
Letter
|
3 |
Basin Electric Power Cooperative |
Erin Fox Dukart |
2023.03.13 |
60 |
60 |
Williams County Grading Permit
Other
|
3 |
Basin Electric Power Cooperative |
Erin Fox Dukart |
2023.03.13 |
61 |
61 |
Copy of 3 Jan. 2023 Williams County Zoning Decision
Other
|
1 |
Basin Electric Power Cooperative |
Erin Fox Dukart |
2023.03.13 |
62 |
62 |
Topsoil Removal Inspection Report
Other
|
67 |
Basin Electric Power Cooperative |
Brett Job, Short Elliott Hendrickson Inc |
2023.03.27 |
63 |
63 |
Pioneer Generation Station Ph IV Progress Report ending March 2023
Progress Report
|
1 |
Basin Electric Power Cooperative |
|
2023.04.06 |
64 |
64 |
Pioneer Generation Station Ph IV Progress Report ending April 2023
Progress Report
|
1 |
Basin Electric Power Cooperative |
|
2023.05.10 |
65 |
65 |
Pioneer Generation Station Ph IV Progress Report ending May 2023
Progress Report
|
1 |
Basin Electric Power Cooperative |
|
2023.06.09 |
66 |
66 |
Pioneer Generation Station Ph IV Progress Report ending June 2023
Progress Report
|
1 |
Basin Electric Power Cooperative |
|
2023.07.12 |
67 |
67 |
Pioneer Generation Station Ph IV Progress Report ending July 2023
Progress Report
|
1 |
Basin Electric Power Cooperative |
|
2023.08.17 |
68 |
68 |
Pioneer Generation Station Ph IV Progress Report ending August 2023
Progress Report
|
1 |
Basin Electric Power Cooperative |
|
2023.09.08 |
69 |
69 |
Pioneer Generation Station Ph IV Progress Report Ending September 2023
Progress Report
|
1 |
Basin Electric Power Cooperative |
|
2023.10.06 |
70 |
70 |
Pioneer Generation Station Ph IV Progress Report Ending October 2023
Progress Report
|
1 |
Basin Electric Power Cooperative |
|
2023.11.28 |
71 |
71 |
Pioneer Generation Station Ph IV Progress Report Ending November 2023
Progress Report
|
1 |
Basin Electric Power Cooperative |
|
2023.12.06 |
72 |
72 |
Pioneer Generation Station Ph IV Progress Report Ending December 2023
Progress Report
|
1 |
Basin Electric Power Cooperative |
|
2024.01.23 |
73 |
73 |
Pioneer Generation Station Ph IV Progress Report Ending January 2024
Progress Report
|
1 |
Basin Electric Power Cooperative |
|
2024.03.05 |
74 |
74 |
Pioneer Generation Station Ph IV Progress Report Ending February 2024
Progress Report
|
1 |
Basin Electric Power Cooperative |
|
2024.03.05 |